This page shows a sample Skyline Report.
This report tracks the progress of Preservation Work Lists. It has a Skyline box for each Preservation Work List, with Planned Dates based on either Due Date or Target Date. It is available for both Greenfield and Brownfield projects.
· Green boxes - indicate that the Preservation Work List has been signed off and is marked Complete.
· Red boxes - indicate that the Preservation Work List Due Date is before today's date, or it is signed off and marked as Not Complete.
· White boxes - indicate that the Preservation Work List has not been signed off and has a Due Date of either today or in the future.
· Orange boxes - indicate the Preservation Work List is marked as "in Progress" in the GoPreserve® Companion App. These boxes are only shown if a project uses the GoPreserve® Companion App.